Prince2-Practitioner Exam Topic 2 Question 13 Discussion:
Question #: 13
Topic #: 2

Which of the following activities is the Executive responsible for?


A.

Ensure the desired outcome of the project is specified


B.

Responsible for the benefits review plan


C.

Assess and update the Business Case at the end of each stage


D.

Responsible for the Benefits Review Plan post project