Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PRINCE2 7 Practitioner (7th Edition) Exam Prince2-Practitioner Question # 11 Topic 2 Discussion

PRINCE2 7 Practitioner (7th Edition) Exam Prince2-Practitioner Question # 11 Topic 2 Discussion

Prince2-Practitioner Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2

If Project tolerances were threatened, who needs to be notified?


A.

Project Board


B.

Project Manager


C.

Corporate or Programme Management


D.

Executive


Get Premium Prince2-Practitioner Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.