Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?
The Senior User within the PRINCE2 project management team represents the interests of those who will use the project’s products and benefit from their operation after the project is complete. This role is responsible for specifying the needs of users, ensuring the solution meets these needs, and is capable of delivering the anticipated benefits. References: PRINCE2 Foundation manual, PRINCE2 official resources