PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 76 Topic 8 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 76 Topic 8 Discussion

Prince2-Foundation Exam Topic 8 Question 76 Discussion:
Question #: 76
Topic #: 8

Which is a purpose of the Controlling a Stage process?


A.

Produce a Team Plan for the work to be assigned to a Team Manager


B.

Select and implement actions that will resolve deviations from a plan within tolerance


C.

Obtain approvals for products delivered in a Work Package


D.

Update a Project Plan to incorporate the actuals from a Stage Plan


Get Premium Prince2-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.