Prince2-Foundation Exam Topic 7 Question 64 Discussion:
Question #: 64
Topic #: 7

The project board needs to confirm that there is enough information to initiate the project.

What should the project board review?


A.

Project brief


B.

Business case


C.

Benefits management approach


D.

Project plan