The goal of the 'implement' step within the recommended risk management procedure in PRINCE2® is to prepare specific management responses to the identified risks. This involves developing strategies to enhance opportunities and reduce threats to the project's objectives, ensuring that appropriate responses are ready for implementation.References: = PRINCE2® 7 Foundation handbook and online resources