A minimum requirement for applying the change theme in PRINCE2® is to identify whether an issue has the potential to affect the continuation of the project. This involves assessing the impact of potential changes or issues on the project's objectives and deciding whether they warrant considering the project as unviable in its current form.References: = PRINCE2® 7 Foundation handbook and online resources