PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 23 Topic 3 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 23 Topic 3 Discussion

Prince2-Foundation Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3

Which should be provided by corporate or programme management before the Starting up a Project process commences?


A.

A Project Brief


B.

Sufficient information to identify the prospective Executive


C.

The Project Initiation Documentation


D.

Authority to initiate a project