The objective of the Starting up a Project process in PRINCE2 includes ensuring that the roles and responsibilities are defined before the project is formally initiated. This includes identifying who will be responsible for creating the Project Plan. References: PRINCE2® Foundation Training Manual; PRINCE2® 2017 Foundation handbook.