PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 127 Topic 13 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 127 Topic 13 Discussion

Prince2-Foundation Exam Topic 13 Question 127 Discussion:
Question #: 127
Topic #: 13

When is a work breakdown structure MOST useful?


A.

When there are multiple work packages with a mix of internal and external resources


B.

in a simple project with one work package for the work of a small team


C.

When establishing a change authority aligned to project tolerances


D.

When assuring business, user and supplier aspects of project performance


Get Premium Prince2-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.