PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 115 Topic 12 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 115 Topic 12 Discussion

Prince2-Foundation Exam Topic 12 Question 115 Discussion:
Question #: 115
Topic #: 12

Which action should the project manager take when reviewing progress to assess the 'health' of a stage?


A.

Capture lessons that may assist in the monitoring and control of this project


B.

Review the quality of the relationships in the organizational


C.

Increase the frequency of event-driven controls to monitor stage progress


D.

Identify whether issues are resolved in a timely manner or left unmanaged


Get Premium Prince2-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.