The principle of 'manage by exception' in PRINCE2® involves setting tolerances for each project objective to establish clear limits of delegated authority. This allows for efficient use of management time and enables project managers to make decisions within the tolerance limits, while escalating issues that go beyond these limits. References: PRINCE2® Foundation Handbook, Manage by Exception section.