PRINCE2 Agile Foundation (Version 2) Exam PRINCE2-Agile-Foundation Question # 29 Topic 3 Discussion

PRINCE2 Agile Foundation (Version 2) Exam PRINCE2-Agile-Foundation Question # 29 Topic 3 Discussion

PRINCE2-Agile-Foundation Exam Topic 3 Question 29 Discussion:
Question #: 29
Topic #: 3

What needs to happen when new detailed requirements are added to a timebox?


A.

Requirements of a similar level of effort should be removed


B.

More people should be added to the delivery team


C.

The delivery milestones should be reviewed and re-planned


D.

Formal change control should be applied


Get Premium PRINCE2-Agile-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.