PRINCE2 Agile Foundation (Version 2) Exam PRINCE2-Agile-Foundation Question # 27 Topic 3 Discussion

PRINCE2 Agile Foundation (Version 2) Exam PRINCE2-Agile-Foundation Question # 27 Topic 3 Discussion

PRINCE2-Agile-Foundation Exam Topic 3 Question 27 Discussion:
Question #: 27
Topic #: 3

Which statement about the ‘be on time and hit deadlines’ target is CORRECT?


A.

It allows change to be handled dynamically


B.

It is achieved by keeping the delivery teams stable


C.

It helps with planning dependencies within a project


D.

It ensures that the level of quality is protected