PRINCE2 Agile Foundation (Version 2) Exam PRINCE2-Agile-Foundation Question # 27 Topic 3 Discussion

PRINCE2 Agile Foundation (Version 2) Exam PRINCE2-Agile-Foundation Question # 27 Topic 3 Discussion

PRINCE2-Agile-Foundation Exam Topic 3 Question 27 Discussion:
Question #: 27
Topic #: 3

Which TWO project board responsibilities are specifically assigned to the senior user?

1) Demonstrating the achievement of benefits.

2) Specifying the needs of those impacted by the outputs.

3) Balancing business, user and supplier demands.

4) Ensuring that the project delivers value for money.


A.

1 and 2


B.

2 and 3


C.

3 and 4


D.

1 and 4


Get Premium PRINCE2-Agile-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.