Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PRINCE2 Agile Foundation (Version 2) Exam PRINCE2-Agile-Foundation Question # 16 Topic 2 Discussion

PRINCE2 Agile Foundation (Version 2) Exam PRINCE2-Agile-Foundation Question # 16 Topic 2 Discussion

PRINCE2-Agile-Foundation Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

Which organizational level is responsible for day-to-day management and decision making within the constraints established by the project manager?


A.

Commissioning


B.

Directing


C.

Managing


D.

Delivering


Get Premium PRINCE2-Agile-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.