Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 617 Topic 62 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 617 Topic 62 Discussion

PMP Exam Topic 62 Question 617 Discussion:
Question #: 617
Topic #: 62

A project manager is assigned to a project that has a tight schedule. Due to recent market changes the marketing team has identified that a few features that were initially in the scope are no longer required

What should the project manager do?


A.

Advise the marketing team that at this stage of the project changes to the scope are no longer accepted


B.

Escalate the issue to the project management office (PMO) and make sure they understand the impact on the schedule due to the change


C.

Update the risk register with input from marketing and sales and highlight the benefits of the features m discussion


D.

Review the change request with the project stakeholders and evaluate the impact of the scope reduction


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.