PMP Exam Topic 62 Question 612 Discussion:
Question #: 612
Topic #: 62

The team's velocity is inconsistent, leading the product owner to believe the team is creating too many points in their user stories.

What should the scrum master do first?


A.

Remind the product owner that their role is to determine what the team should work on during the iteration.


B.

Meet with the product owner for planning and to resize the stories in the backlog.


C.

Invite the product owner to planning poker meetings and get their approval after each story is sized.


D.

Raise this concern with the team and review the performance of the past three sprints.