Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 605 Topic 61 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 605 Topic 61 Discussion

PMP Exam Topic 61 Question 605 Discussion:
Question #: 605
Topic #: 61

A team has been consistently delivering outcomes. However, based on their current performance, it was discovered that their velocity has decreased by 30%.

What should the project manager do to ensure the velocity is under control?


A.

Ask the product owner to look at a minimum of four to eight iterations and replan the velocity for the next iteration based on the team's current performance.


B.

Ask the scrum master to plug gaps in the team's performance by adding a team member to compensate for the velocity decrease.


C.

Request that the team improve their cycle time to compensate for the velocity decrease.


D.

Request the team to improve the lead time, cycle time, and response time individually and track closure.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.