The key stakeholder of an agile project has low visibility of the project's progress. The stakeholder expresses a concern to the project manager about whether or not the scope is moving in the right direction.
What should the project manager do?
A.
Determine alternative solutions to provide improved stakeholder visibility and engagement.
B.
Invite the stakeholder to the demo session and request their feedback about which direction to follow.
C.
Prioritize all of the requirements that are critical to the stakeholder in the next planning session.
D.
Review the scope with the stakeholder, request their feedback, and create an action plan.
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.