PMI Scheduling Professional PMI-SP Question # 74 Topic 8 Discussion

PMI Scheduling Professional PMI-SP Question # 74 Topic 8 Discussion

PMI-SP Exam Topic 8 Question 74 Discussion:
Question #: 74
Topic #: 8

You work as the project manager for BlueWell Inc. Mark, a project team member, has some doubts related to the outputs of the control schedule process. Which of the following is an output of the control schedule process?


A.

Project schedule


B.

Lessons learned


C.

Change request


D.

Activity resource requirement


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.