PMI Scheduling Professional PMI-SP Question # 96 Topic 10 Discussion

PMI Scheduling Professional PMI-SP Question # 96 Topic 10 Discussion

PMI-SP Exam Topic 10 Question 96 Discussion:
Question #: 96
Topic #: 10

John is the project manager for his organization. Management has asked John to fast track his project in order to reach a particular date for the project completion. When John fast tracks the project what project management component must be updated to reflect this decision? Choose the best answer.


A.

Organizational process assets


B.

Cost management plan


C.

Resource calendars


D.

Risk register


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.