PMI Scheduling Professional PMI-SP Question # 94 Topic 10 Discussion

PMI Scheduling Professional PMI-SP Question # 94 Topic 10 Discussion

PMI-SP Exam Topic 10 Question 94 Discussion:
Question #: 94
Topic #: 10

Bonnie is the project manager for her organization. She is developing a strategy to manage the project stakeholders. She wants to identify the key stakeholders, their influence over the project, their interest in project, and an assessment of methods. What can Bonnie create to gain support from the stakeholders in her project?


A.

Stakeholder identification tools


B.

Expert judgment


C.

Stakeholder Analysis Matrix


D.

Communications management plan