PMI-SP Exam Topic 10 Question 92 Discussion:
Question #: 92
Topic #: 10

What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?


A.

Scope Verification


B.

Configuration Management System


C.

Project Management Information System


D.

Integrated Change Control