Question #: 26
Topic #: 3

A PMO professional identified that the strategic project's stakeholders are dissatisfied with the visibility of project progress, citing a lack of visibility into key performance indicators (KPIs) and communication. The project manager ensured that the current PMO reporting process and requirements are being followed.

Which action should the PMO professional take?


A.

Collaborate with stakeholders to confirm their reporting needs and propose enhancements.


B.

Conduct an internal audit of the reporting process to identify inefficiencies and recommend improvements.


C.

Reassure the stakeholders about the reporting system's effectiveness.


D.

Implement stricter reporting requirements to ensure compliance with project standards.