PMI Project Management Office Certified Professional PMI-PMOCP Question # 15 Topic 2 Discussion

PMI Project Management Office Certified Professional PMI-PMOCP Question # 15 Topic 2 Discussion

PMI-PMOCP Exam Topic 2 Question 15 Discussion:
Question #: 15
Topic #: 2

A PMO professional is responsible for supporting programs and projects at a government organization. The PMO professional has been tasked with providing project management tools and information systems that will enable the organization's project managers to achieve their goals effectively.

Which two actions should the PMO professional take? (Choose 2)


A.

Adapt the project management tools and information systems to be compliant with government regulations.


B.

Meet with the project managers to understand their needs and any gaps in using project management tools and information systems.


C.

Provide the project managers with a list of project management tools and information systems in the market and have them pick.


D.

Enhance the organization's project management tools and information systems to meet the specific needs of the project managers.