Question #: 12
Topic #: 2

A PMO professional uses a project portfolio performance dashboard designed using PMO standard metrics. The PMO professional discovers that the lab team is using its own metrics. The lab team's project manager explains that the PMO standard metrics are not meaningful to their team.

How should the PMO professional ensure that the PMO standard metrics are captured, while allowing flexibility for the lab team?


A.

Understand the gaps between the PMO standard metrics and the lab team's metrics and adapt the data collection to ensure that all valuable metrics are reported.


B.

Request the lab team's project manager to stop collecting any lab-team-specific metrics and only report the PMO standard metrics.


C.

Allow the lab team's project manager to continue collecting metrics that are meaningful to their team, having them report "N/A" in place of the PMO standard metrics.


D.

Redesign the PMO project portfolio performance dashboard including a special section displaying the lab team's specific metrics.