PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 43 Topic 5 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 43 Topic 5 Discussion

PMI-ACP Exam Topic 5 Question 43 Discussion:
Question #: 43
Topic #: 5

During a sprint demo, a business representative identifies missing requirements. The agile practitioner realizes that all key stakeholders were not included during requirements detailing.

What should the agile practitioner have done to avoid the situation?


A.

Included the stakeholders in the project planning meeting


B.

Organized an earlier demo to solicit business feedback


C.

Ensured all business leaders signed off on requirements


D.

Engaged key stakeholders periodically to collect requirements