PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 43 Topic 5 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 43 Topic 5 Discussion

PMI-ACP Exam Topic 5 Question 43 Discussion:
Question #: 43
Topic #: 5

A technical problem arises that will likely impact the stories planned for delivery in the current sprint.

What should the Scrum Master do?


A.

Consider adding a story to the next sprint to seek resolution


B.

Immediately solve the problem on behalf of the team


C.

Ask the team to collaboratively work out a solution


D.

Engage a technical manager to assist with finding a solution


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.