PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 16 Topic 2 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 16 Topic 2 Discussion

PMI-ACP Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

What should the agile practitioner do?


A.

Defer starting the design of item B until the second iteration is being planned


B.

Proceed with the design of item B, since it will hasten the second iteration


C.

Escalate the issue to the customer, and obtain their approval before starting the design of item B


D.

Log the issue in the risk register, and request change control board (CCB) approval


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.