Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 16 Topic 2 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 16 Topic 2 Discussion

PMI-ACP Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

Management decides to set up a new project to exploit an emergent market opportunity. Management suggests using an agile approach that is currently working for another project.

What should the agile leader do next?


A.

Conduct a workshop for all key stakeholders to analyze the case and decide on the proper approach.


B.

Suggest an approach that was successful in a previous project.


C.

Accept the manager ' s suggestion and avoid unnecessary conflicts and delays.


D.

Work with the team to analyze the market opportunity and create a tailored agile approach if needed.


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.