A project manager is working on an agile team. A team member mentions that risks threatening the release date of the current sprint are not being addressed.
What should the project manager do to make sure team members are following up on risks?
A.
Hold one daily coordination meeting to determine the reason team members are not following up on risks.
B.
Ask the team to review the executed tasks and follow up on the upcoming threats.
C.
Display the major risks, assumptions, issues, and dependencies (RAID) log visually to highlight the risk status.
D.
Create one sprint to update and follow up on major release risks.
The project manager should ensure that risks are clearly visible to all team members so that everyone is aware of potential issues and can take action as necessary. Displaying the RAID log visually makes it easy for the team to see the status of risks, assumptions, issues, and dependencies in real-time. This encourages the team to follow up on risks and keep them top of mind, facilitating more proactive management of potential threats to the sprint's success. This approach also helps in maintaining transparency and continuous monitoring of risks throughout the sprint.