PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 12 Topic 2 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 12 Topic 2 Discussion

PMI-ACP Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

A project manager is working on an agile team. A team member mentions that risks threatening the release date of the current sprint are not being addressed.

What should the project manager do to make sure team members are following up on risks?


A.

Hold one daily coordination meeting to determine the reason team members are not following up on risks.


B.

Ask the team to review the executed tasks and follow up on the upcoming threats.


C.

Display the major risks, assumptions, issues, and dependencies (RAID) log visually to highlight the risk status.


D.

Create one sprint to update and follow up on major release risks.


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.