PMI-ACP Exam Topic 15 Question 140 Discussion:
Question #: 140
Topic #: 15

A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?


A.

Shared vision statement and sprint goal


B.

Release burnup chart


C.

Velocity metrics


D.

Iteration burndown chart