PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 135 Topic 14 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 135 Topic 14 Discussion

PMI-ACP Exam Topic 14 Question 135 Discussion:
Question #: 135
Topic #: 14

A project team has been working on a new application. The application is technically challenging, because the team is using new technology unknown to the development team and business requirements are unclear. The product owner has been working closely with the stakeholders to ensure alignment with requirements and other issues. The agile lead is working with the team and product owner on the product backlog.

What is the role of the team?


A.

Estimate and define the work items.


B.

Assess user story quality and independent, negotiable, valuable, estimable, small, and testable (INVEST) criteria.


C.

Add features to the product backlog.


D.

Determine if the demand is or is not feasible.


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.