In a planning meeting, the client does not have a clear understanding of the most beneficial features of a project, because there are too many stakeholders with different requirements. How should the project manager approach this project?
A.
Define all requirements so value can be added by delivering a high-level plan at the initiation phase.
B.
Suggest the product owner prioritize the work items by feature to maximize value.
C.
Ask the customer to define the requirements of all stakeholders and select the most valuable features.
D.
Ensure the client has a clear idea about the features and end product before the project starts.
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit