As a team completes their 21st sprint, new information reveals that a number of significant system integrations must be made to ensure the project scope is met. How should the project management plan be adjusted?
A.
Holistically at the project level
B.
At the end of each sprint
C.
At a sprint level after each demo
D.
Periodically, at both the release and project level