PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 74 Topic 8 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 74 Topic 8 Discussion

PMI-200 Exam Topic 8 Question 74 Discussion:
Question #: 74
Topic #: 8

As a team completes their 21st sprint, new information reveals that a number of significant system integrations must be made to ensure the project scope is met. How should the project management plan be adjusted?


A.

Holistically at the project level


B.

At the end of each sprint


C.

At a sprint level after each demo


D.

Periodically, at both the release and project level


Get Premium PMI-200 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.