PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 72 Topic 8 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 72 Topic 8 Discussion

PMI-200 Exam Topic 8 Question 72 Discussion:
Question #: 72
Topic #: 8

PMI-200 Question 72

The team is considering committing to 44 story points for the upcoming sprint. Based on the

velocity chart, what advice should the scrum master offer the team?


A.

Reduce the commitment to 40 story points to ensure a higher chance of meeting the commitment.


B.

Maintain a commitment of 46 story points, representing the most frequently completed velocity.


C.

Increase the commitment to 48 story points to push the team toward higher performance.


D.

Commit to 44 story points as it aligns with the team's average velocity for completed story points.


Get Premium PMI-200 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.