Based on the velocity chart, the team has completed 43, 42, 44, and 46 story points in previous sprints. The average number of completed story points is 43.75, and committing to 44 story points for the upcoming sprint aligns closely with this average. It offers a realistic target that takes into account the team's capacity while providing a reasonable chance of completing the planned work within the sprint.