PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 61 Topic 7 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 61 Topic 7 Discussion

PMI-200 Exam Topic 7 Question 61 Discussion:
Question #: 61
Topic #: 7

During backlog refinement, the team uses an online planning poker tool for estimation. The junior developers change their number of story points after they see the estimations provided by the developers. The junior developers state that the reason for this is that they do not have enough experience and do not want to be blamed for sizing it wrong.

What should the scrum master do?


A.

Ask the developers to keep their estimation so that the team is transparent with their level of understanding of work.


B.

Agree with the team to keep their estimation as the final number of story points will be the average of all team members.


C.

Propose to consider the estimations of only senior developers and have the junior developers learn from them.


D.

Encourage the team to keep their estimation as this will help surface different constraints and assumptions that others might have missed.