A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?
A.
Capture risks and make them visible, and use a burn down chart to focus on reducing risks early in the project.
B.
Ask the scrum master to extend the sprint's duration to allow more time to work through technical issues.
C.
Place the impacted stories on the story board, and use daily stand ups to make the product owner aware of the technical issues.