As part of the organizational change, all project teams within the digital channel’s portfolio have been directed to move from 3-week iterations to 2-week iterations. The development team is frustrated as they think there will not be enough time to test. The product owner does not like this change as it will increase the number of ceremonies.

Which two actions should the scrum master take? (Choose two.)


A.

Proactively engage the resource managers to lead the team and provide the required support.


B.

Request the enterprise coach and human resources support the team with the transition.


C.

Document the pros and cons and review with stakeholders to determine the dependencies.


D.

Protect the team from disruptions and seek an exemption for status quo.


E.

Assess the impacts of the change and brainstorm potential solutions.