PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 41 Topic 5 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 41 Topic 5 Discussion

PMI-200 Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

An organization is using a predictive approach to managing projects. The executives like to see more deliverables in a short time and require that the milestones be achieved on time.

What value can the organization gain by moving to an iterative approach?


A.

New tools that deliver iterative and incremental work


B.

A more predictable delivery schedule and better quality


C.

Higher levels of activity-based planning and user histories


D.

Increased focus on the value and benefits delivered


Get Premium PMI-200 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.