PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 30 Topic 4 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 30 Topic 4 Discussion

PMI-200 Exam Topic 4 Question 30 Discussion:
Question #: 30
Topic #: 4

What is the disadvantage of using velocity as a measure of team efficiency in agile approaches?


A.

Capacity planning will not be accurate.


B.

Inaccurate pressure on customers.


C.

Quality increases while output decreases.


D.

Delivery speed increases while morale decreases.


Get Premium PMI-200 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.