PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 28 Topic 3 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 28 Topic 3 Discussion

PMI-200 Exam Topic 3 Question 28 Discussion:
Question #: 28
Topic #: 3

A newly formed development team experienced difficulty with accurately estimating product backlog items. As a result, the team failed to deliver all of the features in the sprint backlog for the past two iterations.

What should the team do to improve the accuracy of their estimates?


A.

Decrease the sprint time box until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint


B.

Discuss estimating techniques in the daily scrum meeting


C.

Increase the size of the development team until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint.


D.

Begin tracking estimated effort metrics as an input to performance evaluation


Get Premium PMI-200 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.