Question #: 19
Topic #: 2

An organization wants to execute a corporate website redesign project using Scrum. There is an experienced pool of agile team members from a previous project, as well as a pool of available internal team members with some Scrum background.

What should be considered when selecting the team?


A.

Review any reports of conflict between each of the team members over the last two years, and select only those with a track record of working well together.


B.

Ensure there is a balanced mix of people who are experts and members with broad experience based on the work to be performed and determine training needs.


C.

Ensure that none of the team members are geographically dispersed so that all team members can be colocated.


D.

Review each team member's contributions to the velocity of their previous projects and select the highest performers.


Get Premium PMI-200 Questions