PMI-200 Exam Topic 15 Question 144 Discussion:
Question #: 144
Topic #: 15

During agile training, an aspiring scrum master with experience in predictive projects asks about the differences between the Kanban approach and the agile approach.

How should the agile trainer respond?


A.

The Kanban approach relies on storyboards.


B.

The Kanban approach focuses on adaptive, simultaneous workflows.


C.

There are no work-in-process limits in the Kanban approach.


D.

Kanban teams employ a pull system.