During a retrospective meeting, a team develops a large list of initiatives All will have a positive impact and improve team performance What should the agile coach do next?


A.

Positively acknowledge the list and share it with management


B.

Immediately have the team implement the initiatives


C.

Help the team choose one or two initiatives for immediate implementation


D.

Ask the team to choose and implement the most complex initiative