Question #: 110
Topic #: 12

A team member is stressed due to a heavy workload, while other team members have some slack in their schedules How should the team lead address this?


A.

Inform management and suggest that additional resources may be required


B.

Discuss the issue with the team in the daily stand up meetings


C.

Meet personally with the stressed team member to brainstorm ways to better manage their time


D.

Begin tracking the stressed team member's tasks in a separate backlog for additional analysis and reporting