The productivity of an agile team has fallen significantly in the last sprint. The team members have not mentioned any impediments but seem to be fatigued.
What should the agile practitioner do?
A.
Discuss the issue with the team at the next daily standup meeting.
B.
Discuss the issue with the team at a special meeting for this purpose.
C.
Discuss the issue with the project stakeholders at a special meeting for this purpose.
D.
Discuss the issue with the team at the next project retrospective.
Chosen Answer: