PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 3 Topic 1 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 3 Topic 1 Discussion

PMI-200 Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

A project team meets to estimate user stories for a sprint While an important non-functional requirement must be delivered in the sprint the estimate exceeds sprint capacity.

What should the team do?


A.

Estimate only functional requirements that will impact product quality


B.

Add team resources


C.

Refer the issue to the product owner


D.

Break non-functional requirements into those that can be delivered in the given sprint


Get Premium PMI-200 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.