Question #: 1
Topic #: 1

An agile team is continuously interrupted by stakeholders wanting to ask product backlog questions. Distractions can have a negative impact on value delivery and quality.

Who is responsible for protecting against distractions?


A.

Product owner


B.

Project manager


C.

Agile leader


D.

Developers