PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 198 Topic 20 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 198 Topic 20 Discussion

PMI-100 Exam Topic 20 Question 198 Discussion:
Question #: 198
Topic #: 20

A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:


A.

To the project management plan.


B.

To the risk register.


C.

In the scope verification processes.


D.

And their impact to the project in terms of time, cost, and risk.


Get Premium PMI-100 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.