Question #: 197
Topic #: 20

What is one of the objectives of Project Risk Management?


A.

Decrease the probability and impact of an event on project objectives.


B.

Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.


C.

Increase the probability and impact of positive events.


D.

Removal of project risk.