PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 11 Topic 2 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 11 Topic 2 Discussion

PMI-100 Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2

Which process determines the risks that might affect the project?


A.

Perform Qualitative Risk Analysis


B.

Identify Risks


C.

Plan Risk Management


D.

Perform Quantitative Risk Analysis